A solar project needs a clean handoff between quote, design, permit, inspection, and utility interconnection. Keep those steps separate from energy-savings estimates.
Use this guide to organize solar quote review, permit documents, inspection timing, inverter checks, net-metering or self-generation forms, and utility interconnection steps.
When to use this guide
- A homeowner or business is comparing solar quotes and needs to know what electrical documents should be visible.
- A project includes net metering, self-generation, utility export, inverter settings, labels, disconnects, or monitoring.
- Battery-ready or battery-included solar is being discussed and the permit/interconnection path may change.
Inputs to gather
- Site address, utility account, existing service, meter type, roof or ground-mount location, and proposed system size.
- Module model, inverter model, optimizer or microinverter details, AC output current, DC string layout, and cold-weather voltage assumptions.
- Single-line diagram, site plan, labels, disconnects, monitoring, rapid-shutdown or product-specific instructions where applicable.
- Utility application, net-metering or self-generation forms, permit documents, inspection sequence, and commissioning notes.
- Battery, generator, transfer, or critical-load-panel interactions if included or planned later.
Project path matrix
| Situation | Verify first | Keep evidence | Stop if |
|---|---|---|---|
| A homeowner or business is comparing solar quotes and needs to know what electrical documents should be visible. | Site address, utility account, existing service, meter type, roof or ground-mount location, and proposed system size. | Quote, equipment data sheets, single-line, site plan, string layout, inverter settings summary, and label plan. | The system includes batteries, generator interaction, service upgrade, shared metering, commercial demand billing, or export limitation. |
| A project includes net metering, self-generation, utility export, inverter settings, labels, disconnects, or monitoring. | Module model, inverter model, optimizer or microinverter details, AC output current, DC string layout, and cold-weather voltage assumptions. | Permit/inspection documents and utility interconnection or net-metering forms. | The quote does not identify equipment models, AC output, DC string assumptions, or who handles permits and utility forms. |
| Battery-ready or battery-included solar is being discussed and the permit/interconnection path may change. | Single-line diagram, site plan, labels, disconnects, monitoring, rapid-shutdown or product-specific instructions where applicable. | Calculator outputs for string voltage, inverter AC current, and voltage drop with product assumptions. | The installer proposes energizing, exporting, or commissioning before the required local process is complete. |
Working checklist
- Confirm the project branch: A homeowner or business is comparing solar quotes and needs to know what electrical documents should be visible.
- Measure or photograph the first hard inputs: Site address, utility account, existing service, meter type, roof or ground-mount location, and proposed system size. Module model, inverter model, optimizer or microinverter details, AC output current, DC string layout, and cold-weather voltage assumptions.
- Record the decision basis: Net metering and self-generation rules vary by province and utility. Use current utility interconnection process, local authority requirements, product listings, and manufacturer instructions.
- Keep the handoff package together: Quote, equipment data sheets, single-line, site plan, string layout, inverter settings summary, and label plan.
- Stop before work proceeds if this applies: The system includes batteries, generator interaction, service upgrade, shared metering, commercial demand billing, or export limitation.
Workflow
- Review the quote for equipment models, system size, AC output, production assumptions, and exclusions before signing.
- Confirm which party prepares drawings, permit documents, utility forms, and inspection scheduling.
- Use calculator handoffs for string voltage, inverter AC output current, and DC voltage drop only after product data is known.
- Separate local electrical inspection from utility permission to interconnect or export.
- Do not energize or export until the local process, inspection, and utility steps are complete.
Decision checkpoints
- Net metering and self-generation rules vary by province and utility.
- Cold-weather string voltage, inverter AC output, and service capacity can affect design review.
- Battery-ready marketing language is not the same as an approved storage or backup configuration.
- Production estimates are not electrical approval and should be separated from permit/interconnection documents.
Canada-specific checks
- Use current utility interconnection process, local authority requirements, product listings, and manufacturer instructions.
- Province and utility rules can change forms, size thresholds, fees, and timelines.
- Do not claim approval to connect, export, island, or operate from this checklist.
Project package to keep
- Quote, equipment data sheets, single-line, site plan, string layout, inverter settings summary, and label plan.
- Permit/inspection documents and utility interconnection or net-metering forms.
- Calculator outputs for string voltage, inverter AC current, and voltage drop with product assumptions.
- Battery or backup equipment documents if storage is included or future-ready.
Stop and get local review
- The system includes batteries, generator interaction, service upgrade, shared metering, commercial demand billing, or export limitation.
- The quote does not identify equipment models, AC output, DC string assumptions, or who handles permits and utility forms.
- The installer proposes energizing, exporting, or commissioning before the required local process is complete.
Questions to settle before work starts
- Which local authority, utility, property authority, product listing, or manufacturer instruction controls this solar pv and storage decision?
- Which inputs are measured from the field or nameplate, and which are still assumptions from a quote, drawing, or memory?
- Which part of the work will be concealed, energized, interconnected, or purchased before review if the sequence is not controlled?
- Which single assumption would change the equipment choice, installation path, cost, schedule, or inspection timing?
- Who will keep the final photos, calculator outputs, product documents, permit or utility records, and commissioning notes?
Use the related tools
- Use the Solar String Voltage Calculator for cold-weather string voltage screening.
- Use the Solar Inverter AC Output Current Calculator for AC current context.
- Use the PV DC Voltage Drop Distance Calculator when long DC runs are part of the design discussion.
Public reference starting points
- BC Hydro self-generation application - Utility self-generation workflow example.
- Hydro One net metering - Ontario utility net-metering entry point.
- OEB net metering - Regulator context for Ontario net metering.
Local standards and authority note
Confirm PV design, permits, inspection, utility interconnection, product approvals, and net-metering requirements with current local sources.