Chart boundary

Does not size transformer protection, approve primary fuses or breakers, calculate damage curves, or replace manufacturer data.

inrush protection window

Ride-through and protection window

The useful window is between nuisance tripping on inrush and insufficient protection under sustained fault or overload conditions.

Scopetransformers and protectionX-axiscurrent multiple of transformer FLAY-axistime secondsReviewAnnualNextTransformer primary and secondary current calculator
Ride-through and protection windowcurrent multiple of transformer FLAtime secondsTransformer FLArated current markerInrush envelopeshort duration high cur...OCPD curveride-through windowWithstand boundarydamage context
The useful window is between nuisance tripping on inrush and insufficient protection under sustained fault or overload conditions.
Ride-through and protection windowFLAinrush enveloperide-through windowwithstand boundarycurrent multiple of transformer FLAtime seconds
Transformer FLArated current marker

Anchor the protection discussion.

Inrush envelopeshort duration high current

Energization is not a sustained fault.

OCPD curveride-through window

Use manufacturer and rule data.

Withstand boundarydamage context

Protection cannot be judged from inrush alone.

Decision reference

Show why transformer protection must ride through inrush while still protecting the transformer and conductors.

Reference basis: Mersen and Eaton transformer protection application guides.
Curve bandWhat it showsRisk cueHandoff
FLA referenceTransformer rated currentNot enough for protection selectionTransformer current calculator
Inrush regionShort energization currentNuisance trippingManufacturer guide
Damage curveTransformer withstand contextOverprotection or underprotectionEngineering review
Primary device curveFuse or breaker trip bandMiscoordinationTCC chart

Use notes

  • Use this chart as a planning and conversation aid only.
  • Confirm current utility requirements, product markings, manufacturer instructions, and local authority requirements before field work.
  • Use the linked calculator or table when the task needs project-specific arithmetic.