A detached garage or shed feeder combines route planning, load planning, trench work, cable or raceway selection, and inspection timing.
Use this guide before trenching or buying cable for a detached garage, shed, pump, gate, workshop, or outdoor structure fed from a dwelling or service.
When to use this guide
- A homeowner wants lights and receptacles in a detached garage or shed.
- A workshop or future EV charger could make a small underground run become a feeder, subpanel, or service-capacity question.
- A trench route is being planned and inspection-before-backfill timing must be settled.
Inputs to gather
- Structure type, distance, route sketch, source panel, destination equipment, and whether the building is attached or detached.
- Current and future loads: lights, receptacles, heater, compressor, welder, EV-ready conduit, door opener, pump, or subpanel.
- Utility locate ticket, property constraints, frost/settlement concerns, driveway or walkway crossings, and landscaping constraints.
- Wiring method under review: direct-burial cable, PVC conduit, rigid metal conduit, or other authority-approved method.
- Inspection timing, open-trench photos, backfill plan, warning/marker tape, and transition details above grade.
Project path matrix
| Situation | Verify first | Keep evidence | Stop if |
|---|---|---|---|
| A homeowner wants lights and receptacles in a detached garage or shed. | Structure type, distance, route sketch, source panel, destination equipment, and whether the building is attached or detached. | Locate confirmation, route sketch, trench photos, open-trench inspection notes, and backfill photos. | The run crosses driveways, public utility areas, shared property, pools/hot tubs, or unknown underground services. |
| A workshop or future EV charger could make a small underground run become a feeder, subpanel, or service-capacity question. | Current and future loads: lights, receptacles, heater, compressor, welder, EV-ready conduit, door opener, pump, or subpanel. | Load-list worksheet and future-load notes. | The detached structure may need a subpanel, disconnect, grounding/bonding review, or future EV/heater loads. |
| A trench route is being planned and inspection-before-backfill timing must be settled. | Utility locate ticket, property constraints, frost/settlement concerns, driveway or walkway crossings, and landscaping constraints. | Cable or conduit markings, product data, and above-grade transition details. | The trench will be backfilled before inspection timing is confirmed. |
Working checklist
- Confirm the project branch: A homeowner wants lights and receptacles in a detached garage or shed.
- Measure or photograph the first hard inputs: Structure type, distance, route sketch, source panel, destination equipment, and whether the building is attached or detached. Current and future loads: lights, receptacles, heater, compressor, welder, EV-ready conduit, door opener, pump, or subpanel.
- Record the decision basis: A short shed circuit and a detached workshop feeder are different planning jobs. Locate processes, inspection timing, cover, marking, backfill, and detached-structure requirements vary by authority.
- Keep the handoff package together: Locate confirmation, route sketch, trench photos, open-trench inspection notes, and backfill photos.
- Stop before work proceeds if this applies: The run crosses driveways, public utility areas, shared property, pools/hot tubs, or unknown underground services.
Workflow
- Call or request locates before any excavation planning becomes field work.
- Build the load list first so the trench is not sized around only today’s light and receptacle needs.
- Sketch the route, depth-control points, above-grade transitions, and future access needs.
- Choose wiring method only after environment, mechanical protection, pulling, and inspection timing are reviewed.
- Keep the trench open until the required local inspection or review step is complete.
Decision checkpoints
- A short shed circuit and a detached workshop feeder are different planning jobs.
- Future EV, heater, welder, compressor, or subpanel needs can change service-capacity and voltage-drop discussions.
- Direct burial, conduit, and above-grade transitions have different product, protection, and inspection questions.
- Backfill, settlement, and driveway crossings can affect long-term reliability even when the electrical calculation looks simple.
Canada-specific checks
- Locate processes, inspection timing, cover, marking, backfill, and detached-structure requirements vary by authority.
- Underground work may need inspection before concealment or backfill.
- Confirm current Canadian Electrical Code context, local authority requirements, product markings, utility rules, and qualified review before work begins.
Project package to keep
- Locate confirmation, route sketch, trench photos, open-trench inspection notes, and backfill photos.
- Load-list worksheet and future-load notes.
- Cable or conduit markings, product data, and above-grade transition details.
- Voltage-drop and conduit-fill outputs where relevant.
Stop and get local review
- The run crosses driveways, public utility areas, shared property, pools/hot tubs, or unknown underground services.
- The detached structure may need a subpanel, disconnect, grounding/bonding review, or future EV/heater loads.
- The trench will be backfilled before inspection timing is confirmed.
Questions to settle before work starts
- Which local authority, utility, property authority, product listing, or manufacturer instruction controls this wire and raceway decision?
- Which inputs are measured from the field or nameplate, and which are still assumptions from a quote, drawing, or memory?
- Which part of the work will be concealed, energized, interconnected, or purchased before review if the sequence is not controlled?
- Which single assumption would change the equipment choice, installation path, cost, schedule, or inspection timing?
- Who will keep the final photos, calculator outputs, product documents, permit or utility records, and commissioning notes?
Use the related tools
- Use the Load List kVA and Amps Calculator to separate current and future garage loads.
- Use the Voltage Drop Calculator for long detached-building runs.
- Use the Conduit Fill Calculator if a raceway method is selected.
Public reference starting points
- ESA buried wiring information sheet - Ontario underground wiring workflow example.
- Technical Safety BC underground installations bulletin - British Columbia underground installation authority example.
- EleCanada utility locate colour chart - Use as a visual handoff for locate-colour terminology; local locate instructions still govern.
Local standards and authority note
Confirm underground cover, wiring method, bonding, grounding, inspection, and utility locate requirements locally before trench work.